EECA 2024: does your factory need an energy manager?

Published · 6 min read · IoTronix Solution

In short

A factory needs a registered energy manager if it uses 21,600 GJ or more of energy in 12 consecutive months. This is the rule under the Energy Efficiency and Conservation Act 2024 (Act 861), for energy consumers in Peninsular Malaysia or Labuan. The factory must appoint a registered energy manager within 3 months of receiving notice from the Energy Commission. It must then run an energy management system, file a yearly energy efficiency report and submit an energy audit. Each missed duty can be fined up to RM50,000.

What is EECA 2024

The Energy Efficiency and Conservation Act 2024 (Act 861) and its regulations came into force on 1 January 2025 [3]. Suruhanjaya Tenaga (the Energy Commission, ST) enforces the Act [3]. The Act replaced the Efficient Electricity Management Regulations 2008 [3].

The Act applies in Peninsular Malaysia and the Federal Territory of Labuan [4]. It covers large energy consumers, listed buildings and makers and importers of regulated equipment. This post covers the energy consumer part, which is the part that applies to factories.

Separately, buildings listed in the Third Schedule of the Act must display energy intensity labels and meet minimum efficiency standards [3]. A large office block on a factory site may fall under that part as well, so check both.

Which factories count as energy consumers

The Act applies to an energy consumer whose energy use equals or exceeds 21,600 GJ within 12 consecutive months [2]. For a site that uses only electricity, 21,600 GJ works out to 6 million kWh a year [2]. PETRA's NEEAP 2.0 notes that coverage now includes both electrical and thermal energy, in line with EECA [5]. So fuel for boilers, furnaces and dryers also counts towards the total.

Consumption is counted for an activity, business or trade carried out in one place [4]. ST gives the consumer written notice that the Act applies [4]. The deadlines below start from the date of that notice.

The four duties and their deadlines

DutyDeadlineWho does it
Appoint a registered energy manager (REM)Within 3 months of the date of notice [1]Energy consumer
Develop and implement an energy management system (EnMS)Within 1 year of appointing the first REM [1]Energy consumer, led by the REM
Submit the energy efficiency and conservation (EE&C) reportWithin 30 days after the first year from the first REM appointment, then within 30 days after each anniversary [1]Energy consumer
Appoint a registered energy auditor and submit the energy audit reportFirst report within 1 year of the date of notice, then every 5 years [1]Registered energy auditor, for the consumer

ST publishes guidelines for the EnMS, the EE&C report and the energy audit report, and each document must follow them [1].

Fines for each missed duty

Act 861 sets a fine for each duty an energy consumer fails to meet [4]:

  • Not appointing a registered energy manager: fine of up to RM50,000 [4].
  • Not developing and implementing an energy management system: up to RM50,000 [4].
  • Not following ST's guidelines for the energy management system: up to RM20,000 [4].
  • Not submitting the EE&C report: up to RM50,000 [4].
  • Not appointing a registered energy auditor: up to RM50,000 [4].
  • Not submitting the energy audit report: up to RM50,000 [4].

The fines are separate, so a factory that ignores the notice can face several of them.

How EECA fits national energy policy

PETRA's NEEAP 2.0 runs from 2026 to 2035 and is implemented alongside EECA [5]. It sets an energy demand reduction target for the industrial sector of 11.9% by 2035 against business as usual [5]. Industry accounts for about 46% of national energy demand [5]. This is why the Act focuses on large factories.

What your factory should do now

  1. Add up 12 months of electricity in kWh and fuel in GJ, per site. Compare the total with 21,600 GJ [2].
  2. If you are near or above the threshold, find a registered energy manager before ST's notice arrives. You have only 3 months after the notice [1].
  3. Start an energy baseline now: consumption by area, line and major machine, not only the site meter.
  4. Plan the first energy audit, which is due within 1 year of the notice [1].
  5. Keep the data in a form you can reuse for the yearly EE&C report [1].
  6. Name one person in the factory to keep the records the REM and auditor will ask for: bills, fuel invoices and production output.

Get the machine-level energy data your EECA audit asks for

Book a free 30-minute Factory Paperwork Check. We come to your factory, show you the 3 processes that waste the most time, and reply within 1 working day.

Questions

What is the EECA 2024 threshold?

The Act applies to energy consumers that use 21,600 GJ or more within 12 consecutive months [2]. For an all-electric site that is 6 million kWh a year [2], and fuel use counts too [5].

How long do I have to appoint a registered energy manager?

You must appoint a registered energy manager within 3 months of the date of ST's notice [1]. The energy management system follows within 1 year of that appointment [1].

What is the fine for not complying with EECA?

Most energy consumer offences under Act 861 carry a fine of up to RM50,000 each [4]. Not following the EnMS guidelines carries a fine of up to RM20,000 [4].

Sources

  1. [1]Suruhanjaya Tenaga. Energy Consumer: Energy Efficiency and Conservation Act (EECA) 2024
  2. [2]Suruhanjaya Tenaga. What types of energy consumers are affected by EECA 2024?
  3. [3]The Edge Malaysia. Energy efficiency laws kick in tomorrow, says Energy Commission, 2024-12-31
  4. [4]LawPlayer. Energy Efficiency and Conservation Act 2024 (Act 861)
  5. [5]Ministry of Energy Transition and Water Transformation (PETRA). National Energy Efficiency Policy and Action Plan 2026 to 2035 (NEEAP 2.0)