How to Calculate OEE: Formula and Worked Example in RM

Published · 7 min read · IoTronix Solution

In short

OEE is Availability × Performance × Quality. This equals good parts × ideal cycle time ÷ planned production time [1]. An OEE of 85% is often called world class, but most factories are closer to 60% [2]. The difference is hours of good output that you already pay for but do not get.

The OEE formula

OEE = Availability × Performance × Quality [1]. Overall Equipment Effectiveness (OEE) measures how much of a machine's planned time gives good parts at full speed [4]. Each ratio shows one kind of loss [1]:

  • Availability = run time ÷ planned production time. It shows stoppages [1].
  • Performance = (ideal cycle time × total count) ÷ run time. It shows when the machine runs slower than it should [1].
  • Quality = good count ÷ total count. It shows rejects [1].

Multiply the three to get OEE. The short formula gives the same answer: OEE = (good count × ideal cycle time) ÷ planned production time [1]. Planned production time is the shift minus planned breaks [1].

Example: one injection moulding machine, one shift

The inputs below are example figures for a 4-cavity mould on one injection moulding machine. They are not a client result. Use your own numbers.

StepExample inputResult
Shift length12 hours (720 min)
Planned breaks60 minPlanned production time: 660 min
DowntimeMould change 45 min, heater band failure 75 minRun time: 540 min
Availability540 ÷ 66081.8%
Ideal cycle30 s per shot, 4 cavities = 7.5 s per partIdeal in 540 min: 1,080 shots
Performance918 shots actually made ÷ 1,08085.0%
Quality3,672 parts made, 184 rejects: 3,488 ÷ 3,67295.0%
OEE81.8% × 85.0% × 95.0%66.1%

Check with the short formula: 3,488 good parts × 7.5 s = 26,160 s of good output, out of 39,600 s planned. That is 66.1% again.

What 66.1% OEE costs in hours and RM

The missing 33.9% is 224 minutes, or about 3.7 hours out of 11 planned hours. Below, it is split by type of loss. Each hour is valued at an example output of RM150 per machine-hour:

LossMinutes lostAt RM150 per hour (example)
Stops (Availability)120RM300
Running slow: 162 missing shots × 30 s (Performance)81RM202.50
Rejects: 184 parts × 7.5 s (Quality)23RM57.50
Total224RM560 per shift

Stoppages alone take 2 hours a shift. If the machine runs two shifts, six days a week, that is 24 hours a week. The downtime calculator turns that into a monthly figure: 24 hours × 4.3 weeks × RM150 is RM15,480 a month for this one machine, before speed and reject losses. Big companies have the same problem. Siemens estimates the world's 500 largest companies lose 11% of revenue to unplanned downtime. That is almost $1.4 trillion a year [5].

What is a good OEE score?

An OEE of 85% is often called world class. It is based on 90% Availability, 95% Performance and 99% Quality, figures Seiichi Nakajima put in his 1984 book on TPM [2]. Most manufacturers are closer to 60%, and scores under 45% are more common than scores above 85% [2].

Use 85% as a general goal, not a pass mark. Wikipedia notes that 85% is often not the right target [4]. A moulding factory with many short jobs and frequent mould changes will score lower than an extrusion line making one product. First, compare each machine with its own result last month.

The six big losses that lower OEE

Every point of lost OEE comes from one of six losses [3]. When you name the loss, the supervisor knows what to fix.

LossOEE factorOn a moulding floor
Equipment failureAvailability [3]Heater band burns out, hydraulic leak
Setup and adjustmentsAvailability [3]Mould change, colour change
Idling and minor stopsPerformance [3]Part stuck in the mould, cleared in a minute or two
Reduced speedPerformance [3]Cycle set at 34 s instead of 30 s
Process defectsQuality [3]Short shots, flash during stable running
Reduced yieldQuality [3]Rejects at start-up until the mould is warm

Minor stops are the loss that paper records miss most. They last a minute or two and the operator fixes them [3], so nobody writes them down. You only see them as a Performance figure that does not match.

Excel or machine counts: how to get the numbers

You can do this calculation in Excel today. Put planned minutes in B2, downtime minutes in B3, ideal cycle time per part in seconds in B4, total count in B5 and rejects in B6. Then:

  1. Availability: =(B2-B3)/B2
  2. Performance: =(B4*B5)/((B2-B3)*60)
  3. Quality: =(B5-B6)/B5
  4. OEE: multiply the three cells.

The Excel sheet is easy. Getting correct numbers is hard. Downtime minutes come from what the operator remembers at the end of the shift. Counts are copied from the machine display. The report reaches the boss the next day. When the admin staff in charge of the file is on leave, nobody updates the OEE.

With machine counts, the machine gives the numbers, not your staff. A sensor or the machine's own controller records every cycle and every stop, with start and end time. So a two-minute stop is counted the same as a two-hour breakdown. The operator only picks a reason.

See where your machine hours are lost

Put your machines, stop hours and RM per hour into the downtime calculator. Then book a free 30-minute Factory Paperwork Check: we visit and show you your 3 most time-wasting processes.

Questions

What is a good OEE score?

85% is often called world class. It is based on 90% Availability, 95% Performance and 99% Quality [2]. Most manufacturers are closer to 60% [2]. So first aim to do better than your own result last month.

How do I calculate OEE in Excel?

Enter planned minutes, downtime minutes, ideal cycle time, total count and rejects. Then multiply Availability, Performance and Quality [1]. The formulas in this guide work in Excel or Google Sheets without changes.

What are the six big losses in OEE?

Equipment failure and setup reduce Availability. Minor stops and reduced speed reduce Performance. Process defects and start-up rejects reduce Quality [3].

Can I track OEE on old machines without a PLC?

Yes. IoTronix clips sensors onto the machine for cycle count, run/stop and motor current, so no data port is needed. Some people call this an IoT setup. For you, it means the machine records the counts, not your staff.

Is OEE the same as machine utilisation?

No. Utilisation only checks if the machine was running. OEE also counts when the machine runs slower than the ideal cycle, and when it makes rejects [1].

Does a mould change count as downtime in OEE?

Yes. Setup and adjustments, including mould and colour changes, is one of the six big losses. It lowers Availability [3]. Record it with its own reason code. Then you can see how much of your downtime is changeover.

Sources

  1. [1]OEE.com (Vorne Industries). OEE Calculation: Definitions, Formulas, and Examples
  2. [2]OEE.com (Vorne Industries). World-Class OEE: Set Targets To Drive Improvement
  3. [3]OEE.com (Vorne Industries). Six Big Losses in Manufacturing
  4. [4]Wikipedia. Overall equipment effectiveness
  5. [5]Siemens AG. The True Cost of Downtime 2024, 2024