NIMP 2030 was launched on 1 September 2023 [2]. It sets a minimum target of 3,000 smart factories by 2030, under its second mission on technology and digitalisation [1][3]. As at 30 June 2026, MITI counted 93 recognised smart factories. It expects 161 by December 2026 [5][6]. So most of the work is still not done.
What is NIMP 2030
Prime Minister Anwar Ibrahim launched the New Industrial Master Plan 2030 (NIMP 2030) on 1 September 2023 [2]. It is a seven year industrial policy for manufacturing and manufacturing related services. The government estimated it needs about RM95 billion in investment, mostly from the private sector [2].
The plan sets three main targets for 2030 [1]:
- Raise manufacturing value added by 61% to RM587.5 billion, from RM364.1 billion in 2022 [1].
- Grow manufacturing employment by 20% to 3.3 million people [1].
- Raise the median manufacturing salary by 128% to RM4,510 a month, from RM1,976 in 2021 [1].
Those targets are for the whole economy. The smart factory target is the one that affects factories directly, because it counts individual companies.
The four missions, and where smart factories fit
MITI built the plan on four missions, with four support areas on financing, talent, ease of doing business for investors, and governance [1].
| Mission | Focus |
|---|---|
| 1. Advance economic complexity | Move industry into more sophisticated products and activities [1][2] |
| 2. Tech up for a digitally vibrant nation | Smart factories, technology adoption, less reliance on low skilled labour [1] |
| 3. Push for net zero | Industrial decarbonisation and new green growth areas [1] |
| 4. Safeguard economic security and inclusivity | Supply chain security and wider participation in growth [1] |
The smart factory target is a mission based project under Mission 2. The plan links it to three other measures [1]: improved Industry4WRD programmes, a multi tier levy on low skilled foreign workers to push automation, and an automation condition in new manufacturing licences [1]. The Star reports the target as Mission Based Project 2.1 [6].
What the 3,000 target means for a factory
MITI calls 3,000 a minimum target [3]. In February 2025, MITI Deputy Secretary General (Industry) Hanafi Sakri estimated it needs about RM15 billion in financing. That is around RM5 million per company. He said grants and soft loans alone cannot pay for that [3].
For an SME owner, this cost estimate matters more than the 3,000 target. MITI expects commercial banks and development banks such as MIDF to pay much of the cost [3]. Grants exist, but they pay for part of a project, not all of it.
The main programme today is Smart Tech Up. MITI describes it as an extended and improved Industry4WRD policy for SMEs and mid tier companies. It offers guidance, assessment, training, technology and financing support [4]. Press reports describe the grant as reimbursing 50% of project and training costs, up to RM500,000 [7].
Progress so far
MITI counts smart factories in two ways: factories identified under Smart Tech Up, and companies recognised under the Smart Factory Recognition Programme run by SIRIM and MARii [5]. The figures below come from MITI replies in Parliament and from Deputy Minister Sim Tze Tzin.
| Point in time | Reported position |
|---|---|
| January 2026 | 30 factories identified under Smart Tech Up; 71 of 241 registered companies at various stages of implementation [4] |
| 30 June 2026 | 93 recognised in total: 32 under Smart Tech Up and 61 under the Smart Factory Recognition Programme [5] |
| December 2026 (projected) | 161 recognised, with 68 more expected through Smart Tech Up [5][6] |
On 2 October 2026, Sim said Malaysia is still "very far away from 3,000" and that few companies have joined [6]. He said the government is giving priority to manufacturers that do not have the money or skills to change on their own [6].
Other NIMP figures have changed. Manufacturing value added rose 5.9% to RM101.3 billion in the first quarter of 2026 [5]. The median manufacturing wage rose from RM2,659 in 2024 to RM2,775 in 2025 [5], still far from the RM4,510 target [1]. On the financing side, 40 SMEs and mid tier companies had received RM75 million from the NIMP 2030 Strategic Co Investment Fund by 30 June 2026 [5].
What an SME factory owner should do now
- Find out where your factory stands. Smart Tech Up starts with an assessment of your factory. The result decides which project the grant supports [4].
- Pick one bottleneck, not the whole factory. A grant of up to RM500,000 [7] does more on one clear line than on a plan for the whole factory.
- Arrange the rest of the funding early. Grants pay only half [7]. MITI expects banks to fund most of the RM15 billion needed [3]. So talk to your bank or MIDF before you sign with a supplier.
- Record a starting figure before you buy. Assessors look for productivity gains. You cannot show a gain without a starting number.
- Expect more government push. MITI expects 161 recognitions by end 2026 [5]. It still needs more than 2,800 more factories to reach 3,000 by 2030 [3].
Measure your machines before your smart factory assessment
Book a free 30-minute Factory Paperwork Check. We come to your factory, show you the 3 processes that waste the most time. We reply within 1 working day.
Questions
Is the 3,000 smart factory target compulsory for my factory?
No. It is a national target under NIMP 2030 Mission 2 [1]. Joining programmes such as Smart Tech Up is your own choice [4].
How many smart factories does Malaysia have now?
MITI reported 93 recognised smart factories as at 30 June 2026. It expects 161 by December 2026 [5].
Who decides whether a factory counts as a smart factory?
MITI keeps the count. It counts factories identified under Smart Tech Up, and companies recognised under the Smart Factory Recognition Programme run by SIRIM and MARii [5].
Sources
- [1]Hong Leong Bank Global Markets Research. Malaysia: New Industrial Master Plan (NIMP) 2030, 2023-09-04
- [2]Free Malaysia Today. PM launches 'mission-based' industrial master plan, 2023-09-01
- [3]MIDA. Malaysia sets minimum target of 3,000 smart factories by 2030: MITI, 2025-02-20
- [4]EdgeProp (Bernama). 115 companies to be recognised as smart factories by end-2026: Miti
- [5]Bernama. Manufacturing Sector's Performance Remains Positive In 1Q 2026 Under NIMP 2030, 2026-07-23
- [6]The Star. Malaysia still far from target of 3,000 smart factories by 2030, 2026-10-02